Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
George Galatis was a senior nuclear engineer and whistleblower who reported safety problems at the Millstone 1 Nuclear Power Plant, relating to reactor refueling procedures, in 1996.[1][2] The unsafe procedures meant that spent fuel rod pools at Unit 1 had the potential to boil, possibly releasing radioactive steam throughout the plant.[3]
Every 18 months the Millstone 1 nuclear reactor was shut down so the fuel rods that make up its core could be replaced; the old rods, radioactive and burning hot, were moved into a 40-feet-deep body of water called the spent-fuel pool. One-third of the rods were moved into the pool under normal conditions. But in the 1990s Galatis realized that Millstone was routinely performing "full-core off-loads," dumping all the hot fuel into the spent-fuel pool.[1] In addition, the Millstone 1 routine ignored the mandated 250 hour cool-down period before a full core off-load, and sometimes the fuel was moved just 65 hours after shutdown, a violation that melted the boots of one worker. By sidestepping the safety requirements in this way, Millstone saved about two weeks of downtime for each reactor refueling—during which Northeast Utilities had to pay $500,000 a day for replacement power.[
Fukushima Daiichi Nuclear Accident Update (27 March, 03:00 UTC)
As previously reported, three workers at the Fukushima Daiichi nuclear power plant were exposed on 24 March to elevated levels of radiation. The IAEA has received additional information on the incident from the Japanese authorities.
For two of the three workers, significant skin contamination over their legs was confirmed. The Japanese authorities have stated that during medical examinations carried out at the National Institute of Radiological Sciences in the Chiba Prefecture, the level of local exposure to the workers legs was estimated to be between 2 and 6 sieverts.
While the patients did not require medical treatment, doctors decided to keep them in hospital and monitor their progress over coming days.
Fukushima Daiichi Nuclear Accident Update (27 March, 01:15 UTC)
Brief Update on State of Fukushima Daiichi Reactors
AC Power-Units 1 to 4
The restoration work of off-site (i.e., grid) power is still in progress. Off-site power is now connected to Units 1 to 4.
Power distribution panels in the Power Centres of Units 2 and 4 have been connected to the off-site electricity supply, but individual components are still being checked prior to being energised.
The lighting in units 1, 2 and 3 control rooms has been restored. Some instrumentation was recovered for units 1, 2 and 4. However, due to the extent of damage inflicted by the earthquake and tsunami, at present it is not possible to estimate when the equipment may be returned to service.
AC Power-Units 5 and 6
Off-site power has been restored.
Unit 1
Fresh water continues to be injected into the reactor pressure vessel.
As of 23:00 UTC 25 March, white smoke was confirmed to be emanating continuously from the reactor building.
Water sample taken from the stagnant water on the basement floor of the turbine building shows the presence of iodine-131, cesium-137 and cesium-134 to a level comparable to that measured in the turbine building of unit 3 where three workers were exposed to elevated levels of radiation on 24 March.
Unit 2
Fresh water continues to be injected into the reactor pressure vessel.
As of 23:00 UTC 25 March, white smoke was confirmed to be emanating continuously from the reactor building.
The spent fuel pool temperature increased and then stabilized at 57 degrees Celsius as of 00:30 UTC 26 March.
Unit 3
Fresh water is being injected into the reactor pressure vessel.
The temperature at the bottom of reactor pressure vessel has decreased to 100.4 degrees Celsius at 13:00 UTC 26 March. Seawater injection to the spent fuel pool is on-going.
White smoke emanating from the reactor building was still being observed as of 23:00 UTC 25 March.
The dose rate in the reactor containment vessel and suppression chamber continued to decrease to 36.1 sieverts per hour and 1.4 sieverts per hour, respectively, as of 13:00 UTC 26 March.
Unit 4
From March 22 to March 25, 130 to 150 tonnes of seawater was poured into the spent fuel pool each day using a concrete pump. Sea water was also poured in through spent fuel cooling system from 21:05 UTC 24 March to 01:20 25 March.
White smoke was still being observed coming from the reactor building as of 23:00 UTC 25 March.
Unit 5
The reactor remains in cold shutdown. Off-site power has been restored. The reactor water temperature increased to 43.8 degrees Celsius.
The temperature in the spent fuel pool increased to 42.8 degrees Celsius as of 02:00 UTC 26 March.
Unit 6
The reactor remains in cold shutdown. Off-site power has been restored. The reactor pressure vessel water temperature decreased to 21.3 degrees Celsius.
The spent fuel pool water temperature has slightly increased to 30.0 degrees Celsius
Status of Fukushima Daiichi nuclear power station as of 17:00, March 27,
2011
Here is information regarding the status of Fukushima Daiichi nuclear power station from the News Releases by the Government Nuclear Emergency Response Headquarters and Nuclear and Industrial Safety Agency (NISA) officials in the morning on March 27.
�� According to the News Releases, high radiation level in the water was also found in the basement of the turbine building of Unit 1, 2 and 3. The level of radiation on the surface of water was more than 1000 millisieverts (mSv) per hour in Unit-2, 60mSv in Unit-1, 750mSv in Unit-3. NISA officials believe the contaminated water likely came from the reactor rather than the spent fuel pool because the radionuclide detected contained in the fuel and some had short half-lives. TEPCO took immediate action to drain off the water because current situation would cause delay in recovery work. TEPCO already started draining off the water in Unit-1, and also preparing or considering drain off the water in Unit-2 and -3. The water would be sent to condensers in the turbine building.
129.9 microSieverts/hr West Gate Daiichi 9 PM March 27th
1.20 milliSieverts/hr Main Building Daiichi 9 PM March 27th (same at 7:00 PM)
196 micro Sieverts/hr Main Gate 9 PM Daiichi 9 PM March 27th
6.9 microSieverts/hr Measure Point 4 Daina 6 PM March 27th
Unit 3
-At approximately 0:34pm March 27th , Injection of water by concrete pump truck was started. At approximately 2:36 pm, March 27th, the operation was finished. [ETA, I think this is for the spent fuel pool]
UPDATE AS OF 9:30 A.M. EDT, MARCH 27:
Tokyo Electric Power Co. workers on Sunday were using pumps to remove highly contaminated water from the basement of the turbine building of reactors 1 and 2 at the Fukushima Daiichi nuclear power plant.
TEPCO also was preparing to remove water from the turbine building of reactor 3. Removal of the contaminated water is necessary to continue power restoration to the plant.
By Sunday, water injection to the pressure vessels at reactors 1, 2 and 3 had been switched from seawater to freshwater.
Off-site power has been restored to all units and work to connect equipment is ongoing. Progress is being slowed by high radiation levels and wet equipment.
TEPCO said that earlier reports of extremely high radiation levels measured in the water in the basement of the reactor 2 turbine building were inaccurate, according to news reports.
n B.C., detectors measured 0.0000005 millisieverts of Xenon-133 -an isotope that, in addition to being a byproduct of nuclear fission, is used in some medical imaging. That level is significantly less than normal levels of background radiation, said the BCCDC.
Read more: http://www.vancouversun.com/news/Nu...ause+concern/4488277/story.html#ixzz1HooFRYcI
Imaging
Gamma emission from the radioisotope 133Xe of xenon can be used to image the heart, lungs, and brain, for example, by means of single photon emission computed tomography. 133Xe has also been used to measure blood flow.[132][133][134]
Xenon, particularly hyperpolarized 129Xe, is a useful contrast agent for magnetic resonance imaging (MRI). In the gas phase, it can be used to image empty space such as cavities in a porous sample or alveoli in lungs. Hyperpolarization renders 129Xe much more detectable via magnetic resonance imaging and has been used for studies of the lungs and other tissues. It can be used, for example, to trace the flow of gases within the lungs.[135][136] Because xenon is soluble in water and also in hydrophobic solvents, it can be used to image various soft living tissues.[137][138][139]
IAEA Briefing on Fukushima Nuclear Accident (27 March 2011, 13:30 UTC)
1. Current Situation
The situation at the Fukushima Daiichi plant remains very serious.
The restoration of off-site power continues and lighting is now available in the central control rooms of Units 1, 2 and 3. Also, fresh water is now being injected into the Reactor Pressure Vessels (RPVs) of all three Units.
Radiation measurements in the containment vessels and suppression chambers of Units 1, 2 and 3 continued to decrease. White "smoke" continued to be emitted from Units 1 to 4.
Pressure in the RPV showed a slight increase at Unit 1 and was stable at Units 2 and 3, possibly indicating that there has been no major breach in the pressure vessels.
At Unit 1, the temperature measured at the bottom of the RPV fell slightly to 142 °C. At Unit 2, the temperature at the bottom of the RPV fell to 97 °C from 100 °C reported in the Update provided yesterday. Pumping of water from the turbine hall basement to the condenser is in progress with a view to allowing power restoration activities to continue.
At Unit 3, plans are being made to pump water from the turbine building to the main condenser but the method has not yet been decided. This should reduce the radiation levels in the turbine building and reduce the risk of contamination of workers in the turbine building restoring equipment.
No notable change has been reported in the condition of Unit 4.
Water is still being added to the spent fuel pools of Units 1 to 4 and efforts continue to restore normal cooling functions.
Units 5 and 6 remain in cold shutdown.
We understand that three workers who suffered contamination are still under observation in hospital.
2. Radiation Monitoring
Dose rates at the Fukushima site continue to trend downwards.
In 28 of the 45 prefectures for which data are available, no deposition of radionuclides was detected in the period 18 to 25 March. In seven of the other 17 prefectures, the estimated daily deposition was less than 500 becquerel per square metre for iodine-131 and less that 100 becquerel per square metre for caesium-137.
On 26 March, the highest values were observed in the prefecture of Yamagata: 7 500 becquerel per square metre for iodine-131 and 1200 becquerel per square metre for caesium-137. In the other prefectures where deposition of iodine-131 was reported, the daily range was from 28 to 860 becquerel per square metre. For caesium-137, the range was from 2.5 to 86 becquerel per square metre.
In the Shinjyuku district of Tokyo, the daily deposition of iodine-131 on 27 March was 220 becquerel per square metre, while for caesium-137 it was 12 becquerel per square metre.
No significant changes were reported in the 45 prefectures in gamma dose rates compared to yesterday. In general, gamma dose-rates tend to decrease due to the decay of short-lived radionuclides such as iodine-131.
Two IAEA teams are currently monitoring in Japan. One team made gamma dose-rate measurements in the Tokyo region at 8 locations. Gamma dose-rates measured ranged from 0.08 to 0.15 microsievert per hour, which is within or slightly above the normal background. The second team made additional measurements at distances of 30 to 41 km from the Fukushima nuclear power plant. At these locations, the dose-rates ranged from 0.9 to 17 microsievert per hour. At the same locations, results of beta-gamma contamination measurements ranged from 0.03 to 3.1 Megabecquerel per square metre.
The first results of aerial surveys of gamma dose-rates by the Japanese authorities have been received by the Incident and Emergency Centre. These are being analysed and will be presented when more detailed data have been received.
New data from monitoring of the marine environment, carried out from 24 March, 22:55 UTC to 25 March, 03:32 UTC about 30 km offshore, show a decrease in both caesium-137 and iodine 131. The contamination at these locations is influenced by aerial deposition of fallout as well as by the migration of contaminated seawater from the discharge points at the reactor. The measured radiation doses rates above the sea remain consistently low (between 0.04 and 0.1 microsievert per hour). The first results of model predictions received from the SIROCCO Group at the University of Toulouse are being assessed.
Recommendations relating to the restriction of drinking water consumption, based on measured concentrations of iodine-131, remain in place in seven locations (in one location for both adults and infants, and in six locations for infants).
As far as food contamination is concerned, samples taken from 23 to 25 March in five prefectures showed iodine-131 in unprocessed raw milk, but the levels were far below the regulation values set by the Japanese authorities. Caesium-137 was also detected in samples of unprocessed raw milk taken on 23 March in Chiba prefecture, but at levels far below the Japanese regulation values. Caesium-137 was not detected in any of the samples taken from 24-25 March in the other four prefectures.
Based on samples taken on 22 and 24-25 March, three prefectures (Chiba, Ibaraki and Tochigi) reported iodine-131 in celery, parsley, spinach and other leafy vegetables above the regulation values set by the Japanese authorities. Caesium-137 was also detected above the regulation values in one sample of spinach taken on 24 March in Tochigi prefecture, but in the remaining two prefectures, the results were below regulation values.
The Joint FAO/IAEA Food Safety Assessment Team arrived in Tokyo on Saturday. It will meet regulatory officials in various prefectures where food contamination has been detected. The team left for Fukushima early today. The Mission will assist and provide advice on sampling protocols, analytical procedures, data collected to date and actions taken by the Japanese authorities for the control of contaminated foods.
UPDATE AS OF 1:30 P.M. EDT, MARCH 27:
U.S. Navy barges carrying 500,000 gallons of fresh water were nearing the Fukushima Daiichi nuclear power plant Sunday as workers continued to pump cooling water into reactors and spent fuel pools.
Beginning Friday, workers began to switch from sea water to fresh water to cool reactors 1, 2 and 3. The arrival of the barges will maintain the fresh water supply. Engineers are concerned that continued use of sea water will cause corrosion inside the reactors and hinder the cooling process.
Dose rates at the site boundary continued to range from 1 to 3 millirem per hour.
A tiny speck of the fine powder can cause lung cancer in anyone who inhales it and a small amount in the water supply of a large city like Munich could kill hundreds of thousands of people.
JAIF lists the status of each major component of the reactor●Cooling the spent fuel pool
Steam like substance rose from the reactor building at unit 1, 2, 3 and 4 is being observed. Operation of spraying water to the spent fuel pool is being conducted. The operation was conducted 12:34-14:36 in Unit 3 and 16:55-19:25 in Unit 4 on March 27th.
...
<March 27th>
07:30 TEPCO had already started draining off the water in the base of turbine building in Unit-1 to condensers, also preparing in Unit-2, considering in Unit-3 and Unit 4. 12:34-14:36(Unit 3), 16:55-19:25(Unit 4) TEPCO conducted seawater spray to Spent Fuel Pools.
From 10:10 am on March 26th, freshwater (with boric acid) injection was initiated. (switched from the seawater injection) At 06:31PM, Mar 27th, transfer from the fire fighting pump to a temporary motor driven pump was made.
-From 4:55 pm on March 27th, water spray by the concrete pumping vehicle was started and finished at 7:25 pm on March 27th.
No. 34
Status of Fukushima Daiichi nuclear power station as of 20:00, March 28,
2011
Here is information regarding the status of Fukushima Daiichi nuclear power station from the news reports aired by NHK Today.
It is found that there is water accumulated in the tunnel where pipes go through at unit-2 around 15:30 on March 27. It has high radiation that is more than 1000 Sv/hr on the surface. Since the water discovered in the turbine building of unit-2 has same high level radiation, TEPCO is investigating relationship of these 2 cases. (18:40, March 28)
Nuclear Safety Commission expressed the opinion that radioactive material from nuclear fuel once melded possibly have reached outside the containment vessel with water leaked from inside to outside the containment vessel trough unidentified pathway at unit-2. This opinion is based on the fact that water accumulated in the turbine building contain high amount of radioactive material, which is 100,000 times as much as radioactive material contained in water in the reactor at normal operation. Also Nuclear Safety Commission mentioned that operation to inject water to the reactor of unit-2 can be continued even in this situation. (13:25, March 28)
The chief cabinet secretary strongly required not to enter the area to be evacuated in light of the fact that there are some cases in which evacuating persons temporally came back home. (13:25, March 28)
High amount of radioactive material was detected in sea on the northern side of nuclear power station. The seawater contains radioactive iodine-131 in excess of the legal standard by 1150 times. High amount of radioactive iodine was detected also in sea on the southern side of nuclear power station few days ago. Nuclear and Industrial Safety Agency told that radioactive material possibly have moved with the sea current. (13:25, March 28)
Ministry of Defense released movies of the power station taken around 10:00 on March 27 from the helicopter of the self defense force. This movie captured these following scenes.
・The roof of the reactor building collapsed after hydrogen explosion at unit-1.
・Some holes are observed on the roof and steam like white smoke is rising
from these holes at unit-2.
・There is only steal beam upper part of the reactor building and steam is rising at unit-3.
・The wall of the reactor building was blown off and some structure and equipment can be observed at unit-4. Steam is rising from some spots at unit-4.
Dr. Sekimura of Tokyo university pointed out the possibility of damage to the fuel in the spent fuel pool of unit-3 since it would appear that the heavy crane have dropped into the fuel pool in this movie. (05:40, March 28)
It becomes difficult to discharge water accumulated in the turbine building and it would possibly delay the work to restore cooling capability. High amount of radioactive material was detected in water accumulated in the turbine building at unit-1, 2 and 3. Water found in the turbine building of unit-2 contains radioactive material 100000 times as much as radioactive
material contained in water in the reactor at normal operation and radioactivity of water surface is more than 1000mSv/hr. Also water found in the turbine building of unit-1 and unit-3 contains radioactive material, which is 1000 times as much. (04:20, March 28)
End
- At 3:30PM, March 27th, we found that there was water in the trenches of Units 1 to 3. The radioactive emission at the surface of the water was
0.4mSv/h for Unit 1 and over 1,000mSv/h for Unit 2. As for Unit 3, we couldn't have access to the surface because of rubbles. We will continue to monitor water in the trenches.
But I wish you hadn't have given up journalism, in this day and age of self-publishing. The world could use some anti-sensationalist journalists, in my opinion.